We’re Hiring View Open Positions
  Pay Your Bill Online Pay Now
| Back to Case Studies

Foundation Repair Case Studies: Summer Camp Welcome Center – St. Teresa, FL

Problem:

Alpha Foundations was contacted by General Contractor Childers Construction to install Drive Rite™ 2600 Series 2-7/8" Schedule 80 Helical Pipe Piles at the Summer Camp Welcome Center in St. Teresa, Florida.

The live loads of the building changed when the building changed from a sales office to a store & restaurant. Helical piles were used to attach to the existing beams to give the floor the needed support for the new loads. Since the building had a roof and the coastal soils were highly unpredictable. Helical piles were one of the only options.

Location: St. Teresa, FL
Alpha Solution:

Alpha Foundations reviewed the soil information and found a dense layer of soil in the first 10’, followed by 30’ of soil that had less than 5 bps (blows per foot). The poor soil conditions made it necessary to use 2 14" helices installed to an average depth of 7’; however several penetrated as much as 40’ of soil before finding a sufficient layer of soil. The helical piles were installed to 5,000 foot/pounds of torque with a mobile hydraulic anchor drive. Torque readings were monitored by a local engineering firm, Ardaman and Associates.

All piles had 2’ to 5’ of stick up which allowed for the bracket connection. The brackets were specially designed for each beam because of different beam dimensions and applications. A large galvanized saddle bracket as shown to the right was used to make the connection to the beam.

Williams Rod (A coarse all thread) was used to draw any slack out of the bracket and apply pressure to the beam. All brackets were then bolted to the beam with through bolts to prevent any lateral movement.

A load test was set up and performed by Alpha Foundations prior to production pile installation to back up the computer findings of the pile capacities. Installation of the piles took 4 working days to install 66 helical piles.