Services
Our Work
Our Company
About Us
Careers
Service Area
Pay Now
Free Estimate
Case Studies

Foundation Repair Case Studies: Boeing Warehouse Floor Stabilization - Ft. Walton Beach, FL

Thursday, February 19th, 2015 by Lisa Scully

Challenge

The Boeing Company acquired a 80,000-square-foot warehouse from Edwin Watts Golf. Boeing planned to convert the commercial distribution warehouse into a military parts facility. However, a 12,000-square-foot portion of the concrete floor slab had settled as much as six inches and would have to be stabilized and lifted before renovations could begin.

A geotechnical investigation, which included ground penetrating radar and soil borings, showed loose fill soils under the existing slab. Additionally, the original building design called for a six-inch floor slab; however, upon further inspection, the settled portion of the floor slab was found to average 14 inches thick. The cause of the settlement was determined to be a combination of the additional concrete weight and the weak, surficial bearing soils.

Solution

A system of hydraulically-driven push piers was selected to permanently stabilize and lift the settled slab. Slab pier locations were laid out in grid patterns with a maximum spacing generally less than eight feet. Eight-inch-diameter core holes were made through the floor to allow for bracket installation. One hundred twenty-two (122) Model 288 (2.875-inch OD by 0.165-inch wall) slab piers were installed to an average depth of 30 feet and an average drive pressure of 3,200 psi (drive force of 30 kips). The slab piers were connected in series with hydraulic cylinders to uniformly raise the floor back toward level. PolyLEVEL® polyurethane foam was then injected under the slab to fill voids. Once injected, the two liquid urethane components react to form a rapidly setting rigid foam with a compressive strength generally greater than 100 psi. Approximately 5,100 pounds of PL400 were injected below the slab.

Project Summary

Structural Engineer: McCarthy Engineering, Inc.

Geotechnical Engineer: Southern Earth Sciences, Inc.

Certified Installer: Alpha Foundation Specialists, Inc.

Products Installed: (122) Foundation Supportworks® PP288 Slab Piers, Average Depth of 30 feet; PolyLEVEL® PL400, 100 psi Compressive Strength, 6 pcf Typical In-Place Density

About the author
Lisa Scully is the Marketing Manager with Alpha Foundation Specialists. Her mission is to educate you on the symptoms of and solutions to all types of foundation problems. To learn more about Lisa and Alpha Foundations, visit us at www.alphafoundations.com